Klimatec takes part in factory test of new Mitsubishi equipment for London project

Head of Projects Callum Small traveled to Italy last month to take part in a factory test of new Mitsubishi equipment, including full load and max ambient tests.

Klimatec sent Head of Projects Callum to a factory acceptance test in Italy in February, where they carried out a full load test and max ambient test of proposed Mitsubishi equipment for a large London data centre.

Callum Small witnessed the new Mitsubishi equipment in action behind-closed-doors

The team also ran alarm testing and outputs. The witnessed test was completed to ensure the new systems to be installed can achieve and maintain conditions in data halls as detailed in the design specification.